Vattenfall Commits to 254 MW 1,000 MWh Battery at Former German Nuclear Site
Vattenfall took a final investment decision on September 10, 2026, to build its largest battery project to date at the decommissioning Brunsbüttel nuclear plant in northern Germany, targeting operation by end of 2028. The 254 MW / ~1,000 MWh project grew from an earlier 700 MWh design and will connect to the 50Hertz 380 kV transmission grid to absorb surplus wind and solar output. Supplier, battery chemistry, capital cost, and specific commercial applications have not been disclosed.